STREET IMPROVEMENTS ON SOMERSET AVENUE
The improvements will be done in phases & will begin on June 2nd,
lasting for 300 working days.
Phase One will start on the north side of Somerset Ave., starting from the intersection of Redwood Rd. & Somerset Ave. going west to the intersection of Stanton Ave. and Somerset Ave.
Phase Two will start on the south side of Somerset Ave., starting from the intersection of Stanton Ave. & Somerset Ave. going east to the intersection of Redwood Rd. & Somerset Ave.
NO PARKING signs will be posted 72 hours in advance at some of the construction activity areas.